CMMS database

In a great step forward from management, an experienced reliability engineer was hired to help improve plant reliability. The first task for this engineer was to determine the equipment that causing the biggest losses for the business. Having had a CMMS in use for a number of years, this was the obvious place to start. The first place to look was the breakdown data, and this was easy to locate, as all breakdown work requests had been tagged in the CMMS. The breakdown crew had been trained well in the use of the CMMS, and each breakdown had been coded appropriately, which made it easy work to identify chronic losses.

The next place to look was in high-cost areas, so a work order cost report was run that spilt the costs against the equipment hierarchy. Because the equipment hierarchy had been structured well and all relevant hours and materials had been booked against the correct area most of the time, a picture of high-cost items was developed quickly. Matching the chronic losses and costly repairs over the last 12 months, it was easy to find where the effort needed to be applied, so task briefs were raised so maintenance planners could begin planning some critical repairs and engineering could prepare some capital submissions.

The planners developed a plan in the CMMS for the repairs by estimating hours and purchasing materials, which were easy to find as they had all be catalogued and put in bills of materials. In a few instances the planning had already been done, as the work had been done before and the job had been saved as a task list in the CMMS. When all materials were available for the task, the scheduler reviewed his list of work orders from within the CMMS, checked his labor availability through the automated connection to the HR module, and then matched the labor to the task that would be completed in the following week. In the following week, all tasks were completed as they had been planned so well, the planner closed off all the tasks in the CMMS, and this data was now captured for reporting. At the end of the week, a PM compliance measure of 100% was reported, and planning accuracy was spot on. The capital work was still in the approval stage, but at least all the maintenance work was completed on time and to budget.

Is this how it works at your workplace?

Mark Bruneer Image

Mark Brunner has been working for over 30 years in the steel industry in Australia. Currently he is responsible for plant reliability and production data mangement systems the CMMS in his business unit. www.thereliabilityroadmap.com

Upcoming Events

August 9 - August 11 2022

MaximoWorld 2022

View all Events
banner
80% of Reliabilityweb.com newsletter subscribers report finding something used to improve their jobs on a regular basis.
Subscribers get exclusive content. Just released...MRO Best Practices Special Report - a $399 value!
DOWNLOAD NOW
Harmonizing PMs

Maintenance reliability is, of course, an essential part of any successful business that wants to remain successful. It includes the three PMs: predictive, preventive and proactive maintenance.

How an Edge IoT Platform Increases Efficiency, Availability and Productivity

Within four years, more than 30 per cent of businesses and organizations will include edge computing in their cloud deployments to address bandwidth bottlenecks, reduce latency, and process data for decision support in real-time.

MaximoWorld 2022

The world's largest conference for IBM Maximo users, IBM Executives, IBM Maximo Partners and Services with Uptime Elements Reliability Framework and Asset Management System is being held Aug 8-11, 2022

6 Signs Your Maintenance Team Needs to Improve Its Safety Culture

When it comes to people and safety in industrial plants, maintenance teams are the ones who are most often in the line of fire and at risk for injury or death.

Making Asset Management Decisions: Caught Between the Push and the Pull

Most senior executives spend years climbing through the operational ranks. In the operational ranks, many transactional decisions are required each day.

Assume the Decision Maker Is Not Stupid to Make Your Communication More Powerful

Many make allowances for decision makers, saying some are “faking it until they make it.” However, this is the wrong default position to take when communicating with decision makers.

Ultrasound for Condition Monitoring and Acoustic Lubrication for Condition-Based Maintenance

With all the hype about acoustic lubrication instruments, you would think these instruments, once turned on, would do the job for you. Far from it!

Maintenance Costs as a Percent of Asset Replacement Value: A Useful Measure?

Someone recently asked for a benchmark for maintenance costs (MC) as a percent of asset replacement value (ARV) for chemical plants, or MC/ARV%.

OEM recommended maintenance plans

One-third of CEO Terrence O'Hanlon's colleagues think so - at least as a starting point. What do you have to say?