Question: What is the quickest way to improve wrench time?

Answer: Short repairs during PMs (defined as short but complete repairs on problems found during PMs that are done during the PM).

To see how this works let's list the activities of a PM from soup to nuts.

Activity
Get job assignment
Move truck (equipment) from yard (dead line) to bay
Lock out tag out –make it safe
Collect special tools and equipment
Locate, check and collect parts, materials
Travel to job with materials and tools (field and infrastructure)
Quick safety walk down
Perform work (this is the only real wrench time)
Clean up work area on truck
Unlock, un-Tag
Move truck to go line, return to operations
Return tools and excess materials
Do paperwork, work order, closing comments


There are 13 activities and only 1 is productive. One thing is clear. When we can do a second or third planned job on the same asset we would add mostly to the “perform work” time. Let’s put some times into the blocks and see if you agree or not:


Activity Doing PM only in minutes PM + 60 minute short repair
Get job assignment 10 10
Move equipment to work bay or go to equipment 25 25
Lock out tag out 15 15
Collect special tools and heavy equipment 30 30
Locate, check and collect parts, materials 60 60
Travel to job with materials and tools (field and infrastructure) 5 5
Quick safety walk down 10 10
Perform work 90 90+60 = 150
Clean up work area 10 15
Unlock, un-Tag 10 10
Move equipment, return to operations 15 15
Return tools and excess materials 10 10
Do paperwork, work order, closing comments 10 15
Totals 90/300=30% 150/370=40%


Wow, 25% increase in wrench time for that job.

Another advantage

One advantage is that the PM inspectors feel trusted and take greater ownership of the health of the equipment.

There are 5 rules for short repairs

  1. You have to set a maximum time depending on the size of your facility and your type of equipment. Usually the limit is 15 minutes to as long as an hour are common.
  2. The repair must be able to be done safely with the tools that the PM person has with them.
  3. The last rule is that PM mechanic must be already carrying any necessary materials or parts
  4. Of course, the mechanic must have the skills
  5. If in your organization the scope of work on the permit has to be followed and if changed, the permit has to be reissued then short repairs are not for you

Important to code the extra time as CM and not PM on work order if possible

Disadvantages to short repairs that should be known and managed:

  • The skill requirement for PM people for short repairs is significantly higher than for just PM
  • Short repairs require significant judgment (so the short repair doesn’t turn into a long repair or isn’t too disruptive)
  • One thing that you need to accept is that short repairs cause schedule disruptions 
Keep reading... Show less

Upcoming Events

August 9 - August 11 2022

MaximoWorld 2022

View all Events
banner
80% of Reliabilityweb.com newsletter subscribers report finding something used to improve their jobs on a regular basis.
Subscribers get exclusive content. Just released...MRO Best Practices Special Report - a $399 value!
DOWNLOAD NOW
Conducting Asset Criticality Assessment for Better Maintenance Strategy and Techniques

Conducting an asset criticality assessment (ACA) is the first step in maintaining the assets properly. This article addresses the best maintenance strategy for assets by using ACA techniques.

Harmonizing PMs

Maintenance reliability is, of course, an essential part of any successful business that wants to remain successful. It includes the three PMs: predictive, preventive and proactive maintenance.

How an Edge IoT Platform Increases Efficiency, Availability and Productivity

Within four years, more than 30 per cent of businesses and organizations will include edge computing in their cloud deployments to address bandwidth bottlenecks, reduce latency, and process data for decision support in real-time.

MaximoWorld 2022

The world's largest conference for IBM Maximo users, IBM Executives, IBM Maximo Partners and Services with Uptime Elements Reliability Framework and Asset Management System is being held Aug 8-11, 2022

6 Signs Your Maintenance Team Needs to Improve Its Safety Culture

When it comes to people and safety in industrial plants, maintenance teams are the ones who are most often in the line of fire and at risk for injury or death.

Making Asset Management Decisions: Caught Between the Push and the Pull

Most senior executives spend years climbing through the operational ranks. In the operational ranks, many transactional decisions are required each day.

Assume the Decision Maker Is Not Stupid to Make Your Communication More Powerful

Many make allowances for decision makers, saying some are “faking it until they make it.” However, this is the wrong default position to take when communicating with decision makers.

Ultrasound for Condition Monitoring and Acoustic Lubrication for Condition-Based Maintenance

With all the hype about acoustic lubrication instruments, you would think these instruments, once turned on, would do the job for you. Far from it!

Maintenance Costs as a Percent of Asset Replacement Value: A Useful Measure?

Someone recently asked for a benchmark for maintenance costs (MC) as a percent of asset replacement value (ARV) for chemical plants, or MC/ARV%.