How Forgotten Data / Information Can Cost Hundreds of Thousands of Dollars

How Forgotten Data / Information Can Cost Hundreds of Thousands of Dollars

There was a terrible fire in a liquefied petroleum gas (LPG) plant. It destroyed piping and a critical air cooler (fin fan) and damaged pumps, valves, cables and supports. Fortunately, although there were injuries, no one died.

As it commonly happens, this was at the peak of demand, with every barrel of LPG salable at premium price. The downtime cost was more than $500,000 per day.

The owners worked frantically to reengineer the process piping and use alternate coolers. Pumps and valves went to the shop for emergency refurbishment.

Miraculously, the plant was ready for start-up within three weeks.

All went well until the LPG ‘bottoms system’ was started up. This process equipment had not been in the fire and was still as originally designed. Seals on the bottom’s pumps leaked. Each time they were repaired, they leaked again after a matter of hours. All the carbon seal faces in stores were consumed. The shop had to reverse engineer the seal faces and manufacture them from carbon rods while waiting for emergency shipments from the seal vendor.

People remembered issues a long time ago, but none had facts. The records for the plant’s commissioning 15 years prior were incomplete. None of the operating changes or maintenance history had been documented since then. Baseline data for smooth operations hadn’t been captured.

After four days and a total downtime cost of $2,000,000, the last set of OEM seals was installed and everything was ready for start-up. It was so critical that the senior vice president of production was on-site in the control room watching the displays. Twelve years before, he was the operating foreman for the plant.

Suddenly, he said, “Why is the level in the bottoms column less than 40 percent? Everyone knows that when it drops below that, the pump seals leak.”

The level was raised above 40 percent and the seals held.

Everyone would have known the level should be kept above 40 percent if it was documented and available.

The lack of good data governance practices cost the company more than $2,000,000 in lost revenue and every seal leak could have caused another fire.

Malcolm J. Werner

Malcolm J. Werner, P.E., CRL, CMRP, MIAM, is a registered professional mechanical engineer at Jacobs. He has more than 50 years’ experience with equipment design, operation and maintenance. Most of his career has been in assessing O&M performance and designing and implementing improvement programs. His passion is helping people implement best practices.

Reliability.AITM

You can ask "R.A.I." anything about maintenance, reliability, and asset management.
Start
Condition Monitoring with a Digital Camera

The oil and gas industry has become critical for sustained operations and long-term asset reliability. When it comes to condition monitoring, expensive technologies, extensive training, and years of development often come to mind, especially regarding rotating equipment. Tools, such as vibration spectrum analysis, thermal imaging, oil lubrication analysis, and motor current analysis, provide valuable snapshots in time and have been useful in practice for quite some time.

Beyond the Bellows: How One Root Cause Failure Analysis Sparked Cultural Transformation in Refinery Reliability

Sometimes, technical problems are symptoms of deeper cultural and operational issues. This article explores how a deep dive into recurring fluid catalytic cracker (FCC) expansion joint failures led to far-reaching insights, not just about metallurgy and maintenance, but about a refinery's decision-making, communications and reliability culture. It’s a case where the root cause wasn’t just in the metal, but in the mindset.

Quick Time to Value: How to Accelerate ROI in EAM Implementation

Enterprise asset management (EAM) implementation is sometimes misperceived as a complex, resource-intensive endeavor. But that perception is rooted in legacy approaches and outdated systems.

Optimize Operations in 7 Steps: The Strategic Art of Maintenance Planning and Scheduling

Effective maintenance planning and scheduling are essential to prevent unplanned asset failures from dictating your schedules and driving your budgets. In a reactive, unplanned environment, maintenance efforts falter—funds meant for proactive upkeep are instead wasted on waiting for parts, delayed equipment transfers, and emergency fixes that disrupt planned work

Case Study: How Waites Cemented $1 Million in Savings by Eliminating Unplanned Downtime for Buzzi Unicem USA

Minimizing downtime in the cement manufacturing industry is crucial, as each minute of operational delay can lead to significant financial repercussions.

Laying the Groundwork: The Role of Naming Conventions in Spare Parts Management Success

This article outlines best practices for overcoming these hurdles and highlights the foundational elements of a successful spare parts management approach.

Industry 5.0 Is Empowering Today’s Factory Workers and It’s a Long Overdue Revolution

The impacts of Industry 4.0 and its younger sibling, Industry 5.0, fall right down to today’s factory workers. While embedded automation and optimization within the Internet of Things (IoT) and Industry 4.0 have the power to drive new efficiencies, they have also led to the introduction of more complex job roles and tasks, but for fewer frontline workers.

From Data to Action: The Complex Path of Advanced Analytics and Reliability in Industry

In today's industrial landscape, the buzz around advanced analytics is hard to ignore. Companies are increasingly looking to harness the power of data to drive efficiency, reduce downtime, and gain a competitive edge. However, the journey from collecting data to taking actionable steps based on that data is far from straightforward.

Engaging and Retaining the Asset Management Workforce

Employee engagement and retention are critical for the success of asset management organizations. High turnover rates and labor shortages pose significant challenges, impacting operational efficiency, safety and overall workforce morale.

Do or Do Not

Data analysis is critical to understanding problems and decision-making. Analysis that is not followed up by an action is likely a wasted opportunity, but not always.

Upcoming Events

MaximoWorld 2026

August 17 - 20, 2026
View all Events

Upcoming Workshops

View all Workshops

“R.A.I.” the Reliability.aiTM Chatbot

Start
ChatGPT with
ReliabilityWeb:
Find Your Answers Fast
Start