Fundamentals of Maintenance Planning Series

Planning and scheduling functions are the key deliverables of the planning role. This is where the most gains in execution have the potential to be made and acted upon. In some larger organizations these are split, allowing more adequate resources for each role.

The role of the planner needs to cover the full range of the work order system, from input into coding, prioritization and a degree of autonomy in execution. As such these roles, more and more, need to be staffed by skilled and versatile people.

The difference between planning and scheduling needs to be clear within each company. These are differing areas worthy of differing measurement and improvement initiatives.

Planning

Planning can occur at any stage during the life of a works order. An electronic indicator in the work-order systems needs to be able to identify the work-order by status of planning. In this manner works orders requiring parts, procedures, documents, skills or equipment can easily be focused upon. A work order cannot be considered planned until all of these have been considered. As well exception reporting needs to highlight:

  • No resources
  • No $ estimates
  • Incorrect coding

At this point, only, does it become a "Planned" work-order. Not all require planning; this also needs to be included in any indication.

Scheduling

Scheduling is the function of coordinating all of the logistical issues around the issues regarding the execution phase of the work. This can also uncover some areas of planning deficiency, which needs to be captured.

Scheduling is best performed in a capacity-scheduling manner, whereby the following takes place. Most modern systems have the capacity to output data to spreadsheets or similar. This is where the majority of scheduling work needs to occur.

  • Overhead labor hours such as safety and toolbox meetings, break times and training times are to be gathered, along with holidays and scheduled as standing works orders for future analysis of these.
  • Hours for PM completion to be deduced form data in the CMMS. This focuses on ensuring the equipment is maintained to its best levels.
  • Addition of corrective and approved improvement actions as dictated by the prioritization system and operations plan. These are to be Planned works orders only. A guide could be: Age of works orders against priority (As a measure of the priority systems effectiveness)
  • The combination of corrective, preventative and improvement work needs to total the levels set for planned / scheduled work. Although this does constitute the most effective use of labor and resources, there are advantages to planned/unscheduled works. A workable level is 70%- 80% in the initial stages.
  • For example a planned works order may be used during opportune maintenance periods due to major failure or operations reasons. In this instance the benefits of pre-planning become clear. However there does not need to be a rush to repair equipment in an opportune manner simply because it has become available. If there have been higher priority work planned then this needs to retain that focus.

Review of this by week needs to focus on executed works. In this manner re-scheduled works, while important though difficult to fully quantify, can be captured in hour's terms by omission. By setting a level of 70%, for example, you know that the schedule was forecast to that level. Planned / Scheduled work orders are to equal this.

Unplanned and unscheduled work makes up the majority of breakdown works orders generally. However modern systems do contain template work orders. Focusing of these on corrective actions can produce a "planned" breakdown work order.

Works order templates containing all planned information including parts and resources requirements. These can take a lot of the work out of the planning function so that it can be focused more on improvement. Estimation variances, additional tips or instructions, improving the safe working practices and reviewing the stores re-credits can offer areas of improving work order templates. All delivering a more efficient and accurate tool for scheduling and execution.

Templates can also be used to store trouble shooting guides for specific symptoms / fault modes. OEM data and strategy review information is best for providing the detail for these.

Like all changes to maintenance processes this needs to be embedded via a range of initiatives. These include role-specific training, targeted reports for functional purposes and integration of KPI measurement with daily routines. This can happen as part of meeting structures, signs and symbols as well as integration with the salary expectations. (Usually via bonus schemes) Although effective, the behaviors being driven need to be carefully considered.

This is by no means a total explanation of the planning and scheduling function, reporting tools and or processes. It seeks to highlight areas most neglected where immediate improvements, through application, can be easily implemented.

Upcoming Events

August 8 - August 10, 2023

Maximo World 2023

View all Events
banner
80% of Reliabilityweb.com newsletter subscribers report finding something used to improve their jobs on a regular basis.
Subscribers get exclusive content. Just released...MRO Best Practices Special Report - a $399 value!
DOWNLOAD NOW
Defect Elimination in the context of Uptime Elements

Defect Elimination means a lot of things to a lot of people. Uptime Elements offers a specific context for defect elimination [DE] as a success factor on the reliability journey [RJ].

Internet of Things Vendors Disrupting the Asset Condition Management Domain at IMC-2022

Internet of Things Vendors Disrupting the Asset Condition Management Domain at IMC-2022 The 36th International Maintenance Conference collocated with the RELIABILITY 4.0 Digital Transformation Conference [East]

Asset Management Technology

The aim of the Asset Management technology domain is to assure that IT/OT systems are focused on creating the value from the assets and that the business can deliver to achieve organizational objectives as informed by risk.

TRIRIGAWORLD AWARDS at MaximoWorld 2022

TRIRIGAWORLD AWARDS honors excellence in space optimization and facility management, A Reliabilityweb.com event to further advance asset management

IMC-2022 Who's Who: The World's Best Run Companies

The International Maintenance Conference (IMC) provides a fresh, positive community-based curated experience to gain knowledge and a positive perspective for advancing reliability and asset management through people, their managers, the strategy, the processes, the data and the technology. The world’s best-run companies are connecting the workforce, management, assets and data to automate asset knowledge that can be leveraged for huge beneficial decisions.

Uptime Elements Root Cause Analysis

Root Cause Analysis is a problem solving method. Professionals who are competent in Root Cause Analysis for problem solving are in high demand.

Reliability Risk Meter

The asset is not concerned with the management decision. The asset responds to physics

Why Reliability Leadership?

If you do not manage reliability culture, it manages you, and you may not even be aware of the extent to which this is happening!

Asset Condition Management versus Asset Health Index

Confusion abounds in language. Have you thought through the constraints of using the language of Asset Health?

Seven Chakras of Asset Management by Terrence O'Hanlon

The seven major asset management chakras run cross-functionally from the specification and design of assets through the asset lifecycle to the decommissioning and disposal of the asset connected through technology